RENOVATION OF JOSEF GOČÁR SECONDARY CIVIL ENGINEERING TECHNICAL SCHOOL

IN PRAGUE, CZECH REPUBLIC

FACILITY Josef Gočár Secondary Civil Engineering Technical School
COUNTRY Prague, Czech Republic
CUSTOMER Municipal Prague City Council
TYPE OF BUILDING Campus of the secondary school
GENERAL INFORMATION

The project consisted of energy saving measures in all modern school buildings with use area of 5,283 m2.

In the second half of 2009, thermal insulation of the building, supported by a subsidy from Operational Programme Environment commenced. The insulation measures were completed during the spring of 2010.

In 2010, an EPC project was launched. The EPC project has lead to renovation of the boiler house, installation of new air conditioning system and heat pumps and new regulation system. In total these technology measures estimated to save 16.7 GWh of heat and 2.7 GWh of electricity during the whole lifetime of 15 years.

Savings guaranteed in the contract were about 0.1 million EUR/year.

IMPLEMENTED VIA EPC Subsidies
TYPE OF MEASURES Technology measures Thermal envelope measures
START DATE FOR THE PROCUREMENT PROCEDURE December 2009 May 2009
DATE OF CONTRACT SIGNATURE July 2009 September 2009
YEAR OF INSTALLATION MEASURES 2009–2010 2009–2010
CONTRACT DURATION 8 years 7 months
PERIOD OF PROVIDED GUARANTEES FOR ENERGY SAVINGS 8 years 8 years
INVESTMENT VOLUME EUR 0.4 million EUR 1.3 million
TECHNOLOGY MEASURES IMPLEMENTED BY EPC EPC PROVIDER MVV Energie CZ a.s.
IMPLEMENTED MEASURES

Within the EPC project a gas boiler plant, engine room of heating and hot water and air-conditioning were reconstructed, as well as 2 heating pumps (air-water) and modernised measurement and regulation have been installed.

Interventions on the building (wall insulation and replacement of windows and doors) were implemented one year prior to implementation of the EPC project.

FINANCING The investment costs of energy saving measures within the EPC project were in the amount of EUR 0.4 million. The client’s own funds invested in the project amounted to about 20% and the rest of the investment is being repaid from energy savings achieved.
THERMAL ENVELOPE MEASURES CO-FINANCED BY SUBSIDY SUPPLIER OF SUBSIDIZED MEASURES Vltavín Holding, stavební podnik, Ltd. (construction company based in Prague)
IMPLEMENTED MEASURES The client received a subsidy from Operational Programme Environment (OPE) for insulating the building thermal envelope amounting to EUR 1 million i.e. 74% of the total investment costs
TYPE AND SOURCE OF FINANCING Insulation of building thermal envelope
LEARN MORE ABOUT THIS PROJECT Deliverable D3.5: Report on existing performance contracting examples and energy service models.